TPM Capacity & Trade-off Negotiation
Fixed headcount and date: build a trade-off matrix and negotiation notes with Eng Lead.
Capacity math
Trade-off matrix
Negotiation notes
Stakeholder readout
Explicit losers
SCENARIO: 2 engineers × 4 weeks to ship AI Breakthrough + a mentor dashboard the sponsor just added.
You cannot hire. Date is fixed. Eng Lead says estimates are already optimistic.
Template: /assets/templates/tpm-pack/05-capacity-tradeoffs.md
Rubric: /assets/templates/tpm-pack/RUBRIC.md
Must deliver:
1) Capacity math (person-days available vs requested)
2) Trade-off matrix (≥3 options): scope / quality / date / risk
3) Recommendation with explicit losers
4) Negotiation notes with Eng Lead (asks, concessions, parked items)
5) Stakeholder readout (one page)
Submit: matrix + notes + reflection.
Environment setup (start here)
1) Copy 05-capacity-tradeoffs.md + RUBRIC.md. 2) Show the person-day gap in numbers. 3) Complete matrix + negotiation notes + one-pager. 4) Submit + reflection on hardest concession.
Same as Windows.
How do I know it worked?
Common issues
Sign in to complete steps and earn an e-certificate.